Dickerson data center (former Dickerson coal plant)

Also called: Atmosphere Data Centers Dickerson, Terra Energy Dickerson

A company wants to turn the old Dickerson coal plant on the Potomac River into a 360 MW data center campus. It would take river water and reuse old power lines. New county pauses and rules may stop or delay it.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: An earlier 2-building plan was approved in 2024. A bigger 5-building, 360 MW plan is pending; a public hearing is set for Nov. 12-13, 2026. County pauses and a ban may block it.

πŸ•’ Latest update (July 28, 2026): County Council passed an 18-month data center moratorium (Bill 19-26E) and a separate prohibition (Ordinance 20-35).

πŸ—“οΈ Public meeting: Nov 12, 2026
Montgomery County public hearing on the updated plan. Anyone can come and speak.
Hearing continues Nov. 13.

What we know

  • πŸ“ WhereFormer Dickerson Generating Station on the Potomac River, about 2 miles west of Dickerson, Unincorporated Montgomery County, Montgomery County
  • 🏒 CompanyAtmosphere Data Centers
  • ⚑ Power it needs360 megawatts (about as much as 288,000 homes)
  • πŸ”Œ Where the power comes fromWould reuse the old coal plant's power lines and substation; includes a large battery storage facility.
  • πŸ’§ WaterPotomac River (permit sought to withdraw up to 2 million gallons on peak days)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2022
    Retired coal plant was sold to Terra Energy.
  • 2024
    Montgomery County approved Terra Energy's plan for a two-building data center and battery facility.
  • 2025
    Atmosphere applied for a state permit to take up to 2 million gallons a day from the Potomac on peak days.
  • May 2026
    Atmosphere refiled a bigger plan: five buildings, 360 MW.
  • June 12, 2026
    County Executive paused data center permits for six months (Executive Order 109-26).
  • July 28, 2026
    County Council passed an 18-month data center moratorium (Bill 19-26E) and a separate prohibition (Ordinance 20-35).

Local votes and rules

⏸️ Pause on new data centers

The county council voted 11-0 to pause new data center permits for 18 months, until early 2028 (Expedited Bill 19-26). It replaces the county executive's six-month pause. Existing data centers are not affected. The developer of the Dickerson project said the pause applies to it.

July 28, 2026

πŸ—ΊοΈ Zoning change

The county council passed a zoning change (ZTA 26-01) that sets a legal definition of a data center and closes loopholes. An advocacy group reports it also blocks data centers larger than 25 megawatts.

July 28, 2026

βš–οΈ Court case

Atmosphere Data Centers, which wants to build in Dickerson, appealed the county executive's six-month pause to the county's zoning hearings office. The council's 18-month pause later replaced the six-month pause.

July 2026

⏸️ Pause on new data centers

County Executive Marc Elrich ordered the permits department to stop taking and processing permit applications for new data centers for six months. The council's 18-month pause replaced it in July 2026.

June 12, 2026

πŸ“Œ Other

County Executive Marc Elrich proposed data center rules: stricter limits on diesel generator pollution and noise, data centers making at least 80% of their own power, industrial zones only, and public hearings.

Jan 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Dickerson data center: Maryland Data Center Series Β· Nature Forward Β· Aug 14, 2026