Hut 8 River Bend AI data center campus
Also called: River Bend campus
Hut 8 is building an AI data center campus on about 611 acres in southern West Feliciana Parish. The first tenant, Fluidstack, will run computers for Anthropic. Entergy will supply 330 megawatts at first.
Where things stand: Approved by the parish in Jan. 2025. Under construction; first data hall due in 2027.
🕒 Latest update (2026): Parish approved a $10 million early payment from Hut 8 in place of property taxes.
What we know
- 📍 WhereNear U.S. 61 and Louisiana Highway 964, south of St. Francisville, near the River Bend nuclear plant, Unincorporated West Feliciana Parish, West Feliciana Parish
- 🏢 CompanyHut 8
- 👤 Built forFluidstack (for Anthropic), backed by Google
- 🌳 Size611 acres
- ⚡ Power it needs330 megawatts (about as much as 264,000 homes)
- 🔌 Where the power comes fromEntergy Louisiana, starting at 330 megawatts; could grow to 1,000 megawatts.
- 💧 WaterWest Feliciana Parish water system (Hut 8 is paying about $16 million for a new well and water mains)
- 💵 Cost$10 billion
- 💸 Tax breaksState data center equipment sales tax rebate (Act 730) and Quality Jobs program. Hut 8 pays the parish instead of property taxes (PILOT); it advanced $10 million early.
- 👷 Jobs promised75
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will the campus use per day once running? 🙋 I'll find out
- How many diesel backup generators will be on site? 🙋 I'll find out
- Will new power lines be built, and who pays? 🙋 I'll find out
What happened so far
- Jan 6, 2025West Feliciana Planning & Zoning Commission and parish council approved the site plan.
- Dec 17, 2025Hut 8 and the state announced the River Bend campus (up to $10 billion) and a 245 MW lease to Fluidstack.
- 2026Parish approved a $10 million early payment from Hut 8 in place of property taxes.
Local votes and rules
🤝 Agreement with the company
Parish approved a deal where Hut 8 pays $10 million early, on July 1, 2026, out of its future payments in place of taxes. The parish pays it back, with no interest, from the first regular payment due in 2027. Money goes to school pay raises, roads, water and the sheriff.
✅ Approved
Parish officials voted unanimously to approve the River Bend AI data center site off Highway 964.
An aerial photo of the area.
Where this comes from
- Hut 8 Selects Southeast Louisiana as Site of $10 Billion Artificial Intelligence Data Center · Louisiana Economic Development · Dec 17, 2025
- $2.5 billion West Feliciana data center approved with 'aggressive timeline to build' · The Advocate · Jan 7, 2025
- West Feliciana Parish council approves location for $12 billion AI data center · Yahoo News · Jan 7, 2025
- Hut 8 signs 245MW capacity deal with Fluidstack as part of multi-gigawatt partnership with Anthropic · DatacenterDynamics · Dec 17, 2025
- West Feliciana is getting a $10M advance from Hut 8. Here's how it will be used · 10/12 Industry Report · 2026
- Hut 8 Selects Entergy, Southeast Louisiana for $10 Billion Artificial Intelligence Data Center · T&D World · Dec 2025