Send us a tip
Being builtBig (AI-size): 430 megawatts

Applied Digital Delta Forge 1 AI campus (Boyce)

Also called: Delta Forge 1

Applied Digital is building a $3.6 billion AI data center campus near Boyce in Rapides Parish. It could use up to 430 megawatts, the biggest single customer Cleco has ever had. Cleco wants to build a new gas plant partly to serve it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Council of Boyce Town.

Where things stand: Being built Site work began January 2026; first operations expected mid-2027.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (May 26, 2026): The state announced the $3.6 billion Delta Forge 1 campus.

What we know

  • 📍 WhereAlong Interstate 49 near Boyce, Boyce, Rapides Parish
  • 🏢 CompanyApplied Digital
  • 🌳 Size300 acres
  • ⚡ Power it needs430 megawatts (about as much as 344,000 homes)
  • 🔌 Where the power comes fromCleco Power, up to 430 megawatts. Cleco proposed a new 756-megawatt gas plant and a power deal from Texas; Applied Digital pays for new substations and lines.
  • 🗼 New power linesYes
  • ❄️ Coolingclosed-loop cooling
  • 💵 Cost$3.6 billion
  • 💸 Tax breaksState and local sales tax break on data center equipment (Act 730 of 2024).
  • 👷 Jobs promised200

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who will be the tenant? 🙋 I'll find out ·
  • How much water will it use per day? 🙋 I'll find out ·
  • Has the state utility commission approved Cleco's new gas plant? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Jan 2026
      Site development began.
    • May 26, 2026
      The state announced the $3.6 billion Delta Forge 1 campus.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Central Louisiana Secures $3.6 Billion Applied Digital AI Factory Campus · Louisiana Economic Development · May 26, 2026
    2. New Cleco power plant could support $3.6B data center in Rapides Parish · 10/12 Industry Report · 2026
    3. Construction at Boyce data center site along I-49 · Rapides Parish Journal · March 25, 2026
    4. Fact Check: What early documents confirm about Applied Digital's data center coming to Rapides Parish · KALB · June 25, 2026

    See something wrong? Tell us and we'll fix it.