Panattoni wants to build a data center campus called Project Bluegrass on farmland next to the small city of Burgin. It could grow to 1,300 megawatts. The plan depends on Burgin annexing about 500 acres, which would let it avoid the county's new pause on data centers. A local group, We Are Mercer County, opposes it.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Developer wants the city of Burgin to annex about 500 acres of farmland. Annexation got a first reading in July 2026 but no final vote as of late September 2026.

πŸ•’ Latest update (Sept 2026): A Burgin council member walked out of a meeting, which kept the council from voting on the annexation.

What we know

  • πŸ“ WhereFarmland just north of Burgin (proposed to be annexed into the city), Unincorporated Mercer County, Mercer County
  • 🏒 CompanyPanattoni Data Centers
  • πŸ›οΈ Owned byPanattoni
  • 🌳 Size950 acres
  • ⚑ Power it needs1,300 megawatts (about as much as 1,040,000 homes)
  • πŸ”Œ Where the power comes fromKentucky Utilities / LG&E, under their data center rate rules.
  • ❄️ Coolingclosed-loop cooling (developer's statement)
  • πŸ‘· Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • July 2026
    Burgin City Council gave a first reading, 3-2, to an ordinance to annex the land.
  • Aug 2026
    Panattoni posted new details: four buildings on a 950-acre site, with less than half of it built on, and closed-loop cooling.
  • Aug 12, 2026
    Mercer County Fiscal Court passed a one-year pause on data center applications in unincorporated areas. It does not cover land inside Burgin. The developer filed a new annexation request the same day.
  • Sept 2026
    A Burgin council member walked out of a meeting, which kept the council from voting on the annexation.

Local votes and rules

πŸ“Œ Other

Burgin City Council has been weighing a plan to annex farmland north of the city so Panattoni Data Centers can build a hyperscale data center ('Project Bluegrass'). An earlier annexation of over 1,000 acres in July 2026 was voided. At a later meeting, council members left, so there were too few to vote on annexation. The council also moved, on the mayor's tie-breaking vote, toward joining a planning commission. The annexation is not final.

Sept 2026

⏸️ Pause on new data centers

Mercer County Fiscal Court unanimously passed a one-year pause on data centers outside city limits. It does not reach land the city of Burgin may annex for Panattoni Data Centers' planned 'Project Bluegrass' hyperscale data center. The court first approved the idea on July 28, 2026.

Aug 12, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something