ProposedBig (AI-size): 1,300 megawatts

Project Bluegrass (Panattoni data center near Burgin)

Also called: Project Bluegrass, Panattoni Burgin data center

Panattoni wants to build a data center campus called Project Bluegrass on farmland near the small city of Burgin. It could grow to 1,300 megawatts. The plan depends on Burgin annexing hundreds of acres, which would let it avoid the county's pause on data centers. A local group, We Are Mercer County, opposes it.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Mercer County Fiscal Court (for land outside city and town limits).

Where things stand: Proposed Burgin's first try to annex the land in July 2026 was declared null and void, reports say. The city restarted with new boundary lines on Sept. 8, but a council member's walkout stopped the vote. No annexation as of Oct. 7, 2026.

❓ 5 open questions about it: see below.

Last checked Nov 2, 2026.

🕒 Latest update (Sept 8, 2026): Burgin restarted the annexation with adjusted boundary lines. A council member walked out of the meeting, which left no quorum, so no vote was held.

What we know

  • 📍 WhereFarmland just north of Burgin (proposed to be annexed into the city), Unincorporated Mercer County, Mercer County
  • 🏢 CompanyPanattoni Data Centers
  • 🏛️ Owned byPanattoni
  • 🌳 Size950 acres
  • ⚡ Power it needs1,300 megawatts (about as much as 1,040,000 homes)
  • 🔌 Where the power comes fromKentucky Utilities / LG&E, under their data center rate rules.
  • ❄️ Coolingclosed-loop cooling (developer's statement)
  • 👷 Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will Burgin City Council give final approval to the annexation? 🙋 I'll find out ·
  • Which tech company would use Project Bluegrass? 🙋 I'll find out ·
  • How much water will it use, and from which water utility? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or the Burgin annexation map helps. 🙋 I'll find out ·
  • How many acres would Burgin annex? Reports range from more than 500 to more than 1,000. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2026
      Burgin City Council gave a first reading, 3-2, to an ordinance to annex the land.
    • Aug 2026
      Panattoni posted new details: four buildings on a 950-acre site, with less than half of it built on, and closed-loop cooling.
    • Aug 2026
      Burgin's July attempt to annex more than 1,000 acres for the project was declared null and void, WKYT and LEX 18 reported. The reports do not say who declared it.
    • Aug 12, 2026
      Mercer County Fiscal Court passed a one-year pause on data center applications in unincorporated areas. It does not cover land inside Burgin. The developer filed a new annexation request the same day.
    • Sept 8, 2026
      Burgin restarted the annexation with adjusted boundary lines. A council member walked out of the meeting, which left no quorum, so no vote was held.

    Local votes and rules

    ✋ Turned down

    Mercer County Fiscal Court voted down proposed zoning rules that would have allowed large data centers next to the coal-fired E.W. Brown power plant, near Shaker Village. The county's one-year pause stays in place.

    Sept 2026

    📌 Other

    Burgin City Council has been weighing a plan to annex farmland north of the city so Panattoni Data Centers can build a hyperscale data center ('Project Bluegrass'). An earlier annexation of over 1,000 acres in July 2026 was voided. At a later meeting, council members left, so there were too few to vote on annexation. The council also moved, on the mayor's tie-breaking vote, toward joining a planning commission. The annexation is not final.

    Sept 2026

    ⏸️ Pause on new data centers

    Mercer County Fiscal Court unanimously passed a one-year pause on data centers outside city limits. It does not reach land the city of Burgin may annex for Panattoni Data Centers' planned 'Project Bluegrass' hyperscale data center. The court first approved the idea on July 28, 2026.

    Aug 12, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something