Being builtBig (AI-size): 400 megawatts

PowerHouse / Poe data center campus on Camp Ground Road

Also called: PowerHouse Data Centers Louisville Campus

A campus of seven two-story data center buildings, about 1.6 million square feet, on about 150 acres on Camp Ground Road in west Louisville. It could use about 400 megawatts of power when finished; a state report puts the first phase at 130 megawatts in late 2026 and lifetime investment at about $11 billion. Each building gets diesel backup generators. Many neighbors oppose it over air, water and power bill worries.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Jefferson County Fiscal Court (for land outside city and town limits).

Where things stand: Being built Planning Commission approved the site plan in March 2026 (6-1). Site work is underway; first phase was expected to start running in late 2026.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (July 9, 2026): U.S. Rep. Morgan McGarvey wrote to LG&E opposing the project and asking that Louisville families not pay for the power upgrades.

What we know

  • 📍 Where6001 Camp Ground Road (parcel 101204570000), west of Shively, northeast of LG&E's Cane Run power plant, Louisville Metro, Jefferson County
  • 🏢 CompanyPoe Companies and PowerHouse Data Centers
  • 🏛️ Owned byAmerican Real Estate Partners (PowerHouse)
  • 🌳 Size153 acres
  • ⚡ Power it needs400 megawatts (about as much as 320,000 homes)
  • 🔌 Where the power comes fromLG&E power. LG&E is building a new switching station; the campus gets its own substation.
  • 🗼 New power linesYes
  • 💵 Cost$11 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which tech company will use the Camp Ground Road data center? 🙋 I'll find out ·
  • How much water will it use per day, and from which water utility? 🙋 I'll find out ·
  • How many diesel backup generators will be on site? 🙋 I'll find out ·
  • Did the project get any state or local tax breaks? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked USGS satellite images: the parcel still shows woods and fields. The images are older than the 2026 start of site work, so we confirmed the site with the Louisville parcel record instead.

    What happened so far

    • Jan 2025
      Poe Companies and PowerHouse Data Centers announced plans for Kentucky's first hyperscale data center on Camp Ground Road.
    • March 5, 2026
      Louisville Metro Planning Commission approved the revised site plan 6-1 after more than 20 residents spoke against it. No Metro Council vote was needed because the land is already zoned heavy industrial.
    • July 9, 2026
      U.S. Rep. Morgan McGarvey wrote to LG&E opposing the project and asking that Louisville families not pay for the power upgrades.

    Local votes and rules

    ⏸️ Pause on new data centers

    Louisville Metro Council voted 24-1 to pause new data centers for six months, or until it passes full zoning rules. Planners will not accept or process new data center plans. The council added a change so that turning an existing building into a data center is also paused.

    Aug 13, 2026

    📜 Data center rules

    Louisville Metro is writing new zoning rules for data centers (case 25-LDC-0014). The June 2026 draft, revised in July, would ban the biggest data centers (over 500,000 square feet) and keep new ones in industrial areas. The Kentucky Resources Council says the draft lets many data centers up to 250,000 square feet be approved by staff with no public hearing. The Metro Council has not voted yet.

    June 9, 2026

    ✅ Approved

    Louisville's Planning Commission voted 6-1 to approve revised plans for a 1.6-million-square-foot data center on Camp Ground Road near Shively, by Poe Companies and PowerHouse Data Centers. The land was already zoned heavy industrial, so the Metro Council did not have to vote. More than 20 residents spoke against it over pollution, water and power.

    March 5, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. West Louisville data center approved despite opposition · Louisville Public Media · March 5, 2026
    2. Planning commission recommends approval for 1.6m sq ft planned data center in Louisville, Kentucky · Data Center Dynamics · March 2026
    3. Rep. McGarvey opposes Camp Ground Road data center in letter to LG&E · Office of U.S. Rep. Morgan McGarvey · July 9, 2026
    4. Developers plan to build Kentucky's first 'hyperscale' data center in Louisville · Kentucky Lantern · Jan 2025
    5. EPIC Report No. 2026-001: Data Centers in Kentucky · Kentucky Energy Planning and Inventory Commission (UK CAER) · June 2026
    6. Address point 6001 Camp Ground Rd: parcel 101204570000, zoned M3 · LOJIC (Louisville/Jefferson County Information Consortium) · Oct 8, 2026
    7. Jefferson County parcel 101204570000 · LOJIC / Jefferson County PVA · Oct 8, 2026