Proposed

North Campbell Land Co. 50 MW data center (Hopkinsville)

The company that runs a bitcoin mine in Hopkinsville wants to build a second, 50-megawatt data center somewhere else in the city. It says it would pay for a new substation. Hopkinsville is writing rules that would ban data centers of 75 megawatts or more.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Hopkinsville City.

Where things stand: Proposed Proposed in July 2026 while Hopkinsville writes its first data center zoning rules. No application approved.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 27, 2026): At a city hearing on data center rules, North Campbell Land Co. described plans for a 50-megawatt data center and residents raised noise, water and generator concerns.

What we know

  • 📍 WhereA second site in Hopkinsville (exact site not made public), Hopkinsville, Christian County
  • 🏢 CompanyNorth Campbell Land Co.
  • 🏛️ Owned bySphere 3D
  • ⚡ Power it needs50 megawatts (about as much as 40,000 homes)
  • 🔌 Where the power comes fromHopkinsville Electric System. The company says it would pay $8-10 million for a new 65-megawatt substation.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where in Hopkinsville would the 50-megawatt data center go? 🙋 I'll find out ·
  • Will it have diesel backup generators? 🙋 I'll find out ·
  • How much water would it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 27, 2026
      At a city hearing on data center rules, North Campbell Land Co. described plans for a 50-megawatt data center and residents raised noise, water and generator concerns.

    Local votes and rules

    🗺️ Zoning change

    A planning committee voted unanimously to allow data centers only in heavy industrial (I-2) zones, not light industrial (I-1) zones. The change goes next to the full Planning Commission and then the city council. No dates were given.

    Oct 8, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something