USA โ€บ Kentucky โ€บ Marshall County โ€บ Calvert City City
Built & running

Core Scientific data center (Calvert City)

Core Scientific runs a 150-megawatt data center in an old steel mill on Shar-Cal Road in Calvert City. It has mostly been used for bitcoin mining. The building is about 60,000 square feet on 15 acres.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Running since 2019, mostly for bitcoin mining.

๐Ÿ•’ Latest update (2019): Core Scientific's Calvert City data center started running in a former steel mill.

What we know

  • ๐Ÿ“ Where1035 Shar-Cal Road, in a former steel mill (geocoded), Calvert City, Marshall County
  • ๐Ÿข CompanyCore Scientific
  • ๐Ÿ›๏ธ Owned byCore Scientific
  • ๐ŸŒณ Size15 acres
  • โšก Power it needs150 megawatts (about as much as 120,000 homes)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2019
    Core Scientific's Calvert City data center started running in a former steel mill.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Calvert City, Kentucky ยท Core Scientific ยท 2026
  2. See where data center developers are looking to build in Kentucky ยท Kentucky Lantern (via States Newsroom) ยท Aug 16, 2026

See something wrong? Tell us and we'll fix it.