Built & runningBig (AI-size): 150 megawatts
Core Scientific data center (Calvert City)
Core Scientific runs a 150-megawatt data center in an old steel mill on Shar-Cal Road in Calvert City. It has mostly been used for bitcoin mining. The building is about 60,000 square feet on 15 acres.
What happens next?
Where things stand: Built & running Running since 2019, mostly for bitcoin mining.
❓ 2 open questions about it: see below.
📣 Report noise, water or power bill changes
Last checked Oct 8, 2026.
🕒 Latest update (2019): Core Scientific's Calvert City data center started running in a former steel mill.
What we know
- 📍 Where1035 Shar-Cal Road, in the former Gerdau Ameristeel steel mill next to the Tennessee River in Calvert City, Calvert City, Marshall County
- 🏢 CompanyCore Scientific
- 🏛️ Owned byCore Scientific
- 🌳 Size15 acres
- ⚡ Power it needs150 megawatts (about as much as 120,000 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Does Core Scientific plan to switch the Calvert City site to AI computing? 🙋 I'll find out ·
- Which utility powers the site? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked USGS satellite images: the old pin sat on a farm field. The former steel mill on Shar-Cal Road, a long industrial building with a substation beside it, is about 2 km east, so we moved the pin there.
What happened so far
- 2019Core Scientific's Calvert City data center started running in a former steel mill.
🛰️ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- Calvert City, Kentucky · Core Scientific · 2026
- See where data center developers are looking to build in Kentucky · Kentucky Lantern (via States Newsroom) · Aug 16, 2026
- Gerdau Ameristeel, Shar-Cal Road, Calvert City (map feature) · OpenStreetMap Nominatim · Oct 8, 2026
See something wrong? Tell us and we'll fix it.