TeraWulf Muskie Data Campus at EastPark
Also called: Muskie Data Campus
TeraWulf plans a large AI data center campus on about 285 acres in the EastPark industrial park near Ashland. It would start at 500 megawatts in 2028 and could grow to 1 or even 2 gigawatts. Kentucky Power is building a new substation for it. No tech company tenant has been named.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Boyd County Fiscal Court (for land outside city and town limits).
Where things stand: Proposed TeraWulf bought the site in May 2026. First 500 megawatts are planned for late 2028, and 500 more for late 2030.
❓ 6 open questions about it: see below.
Last checked Oct 20, 2026.
🕒 Latest update (Oct 15, 2026): Kentucky Power held a public open house in Boyd County on the new power lines and substation for the campus.
What we know
- 📍 WhereAbout 285 acres in the EastPark industrial park near Ashland, on the Boyd-Greenup county line, Unincorporated Boyd County, Boyd County
- 🏢 CompanyTeraWulf Inc.
- 🏛️ Owned byTeraWulf Inc.
- 🌳 Size285 acres
- ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)
- 🔌 Where the power comes fromKentucky Power (AEP) plans two new power lines and a substation for the site, and a new 760-megawatt gas plant in Lawrence County by 2031. TeraWulf would pay for the lines and the gas plant's financing. The Kentucky PSC must approve.
- 🗼 New power linesYes
- 💵 Cost$4 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which tech company will use the Muskie campus? 🙋 I'll find out ·
- How much water will it use, and from which water utility? 🙋 I'll find out ·
- Will Kentucky Power customers pay for any of the new power equipment? 🙋 I'll find out ·
- Is the site in Boyd County or Greenup County? EastPark sits on the county line. 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
- When will Kentucky Power file the gas plant and power line plans with the Public Service Commission, and what is the case number? 🙋 I'll find out ·
What happened so far
- May 26, 2026TeraWulf announced the Muskie Data Campus in EastPark, near I-64 and next to a landfill, for 1 gigawatt or more.
- Aug 6, 2026TeraWulf told investors the campus could grow to as much as 2 gigawatts.
- Oct 12, 2026Kentucky Power told the Public Service Commission it will seek approval for a new 760-megawatt gas plant in Lawrence County to serve the campus, with TeraWulf paying its financing costs.
- Oct 15, 2026Kentucky Power held a public open house in Boyd County on the new power lines and substation for the campus.
Local votes and rules
⏸️ Pause on new data centers
Greenup County Fiscal Court unanimously passed a six-month pause on data centers, effective right away. It does not apply to TeraWulf's planned 1-gigawatt data center at EastPark industrial park, or to cities in the county. The county judge-executive said the county wants to set rules on noise, lights and more.
⏸️ Pause on new data centers
Boyd County Fiscal Court voted unanimously for a six-month pause on new data centers. The pause does not apply to EastPark industrial park, where TeraWulf plans a large data center. Leaders said EastPark is owned with other counties, so the pause should not block it.
Drag the slider to compare the land before and now.
Where this comes from
- New data center project announced in northeastern Kentucky · WEKU · May 26, 2026
- TeraWulf acquires 1 GW Eastern Kentucky HPC campus to expand AI infrastructure · LEX 18 · May 2026
- TeraWulf tells investors it could double the size of one of its Ky. data center projects · WEKU · Aug 6, 2026
- Kentucky data center developer says it could double in size · Government Technology · Aug 2026
- Kentucky Power to ask state regulator to approve new gas plant for EKY data center · WEKU · Oct 12, 2026
- KY Power will build new infrastructure to support TeraWulf data center project · WEKU · Oct 19, 2026