Proposed

TeraWulf Muskie Data Campus at EastPark

Also called: Muskie Data Campus

TeraWulf plans a large AI data center campus on about 285 acres in the EastPark industrial park near Ashland. It would start at 500 megawatts in 2028 and could grow to 1 or even 2 gigawatts. Kentucky Power is building a new substation for it. No tech company tenant has been named.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: TeraWulf bought the site in May 2026. First 500 megawatts are planned for late 2028, and 500 more for late 2030.

πŸ•’ Latest update (Aug 6, 2026): TeraWulf told investors the campus could grow to as much as 2 gigawatts.

What we know

  • πŸ“ WhereAbout 285 acres in the EastPark industrial park near Ashland, on the Boyd-Greenup county line, Unincorporated Boyd County, Boyd County
  • 🏒 CompanyTeraWulf Inc.
  • πŸ›οΈ Owned byTeraWulf Inc.
  • 🌳 Size285 acres
  • ⚑ Power it needs1,000 megawatts (about as much as 800,000 homes)
  • πŸ”Œ Where the power comes fromKentucky Power (AEP) is building a new 345 kV substation tied to its big 765 kV power lines. AEP is also buying the Longview coal plant in West Virginia.
  • πŸ—Ό New power linesYes
  • πŸ’΅ Cost$4 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 26, 2026
    TeraWulf announced the Muskie Data Campus in EastPark, near I-64 and next to a landfill, for 1 gigawatt or more.
  • Aug 6, 2026
    TeraWulf told investors the campus could grow to as much as 2 gigawatts.

Local votes and rules

⏸️ Pause on new data centers

Greenup County Fiscal Court unanimously passed a six-month pause on data centers, effective right away. It does not apply to TeraWulf's planned 1-gigawatt data center at EastPark industrial park, or to cities in the county. The county judge-executive said the county wants to set rules on noise, lights and more.

July 17, 2026

⏸️ Pause on new data centers

Boyd County Fiscal Court voted unanimously for a six-month pause on new data centers. The pause does not apply to EastPark industrial park, where TeraWulf plans a large data center. Leaders said EastPark is owned with other counties, so the pause should not block it.

July 2026
πŸ›°οΈ See it from above

An aerial photo of the area.