NextEra Energy land options near Garden Plain
NextEra Energy signed options to buy close to 800 acres of farmland near Garden Plain, which residents believe is for a data center. No application has been filed, and Sedgwick County has paused data center applications.
Where things stand: Land options signed; no application. County pause on data center applications runs through Dec. 24, 2026.
π Latest update (July 2025): NextEra vice presidents began signing purchase options with more than 10 landowners for about 800 acres (through January 2026).
What we know
- π WhereBetween 311th St. West and 279th St. West off 21st St. North, near Garden Plain, Sedgwick County
- π’ CompanyNextEra Energy
- π³ Size800 acres
- π€ Secret deal (NDA)Yes. Landowners were asked to sign secret deals (NDAs).
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is NextEra planning a data center near Garden Plain, and for which customer? π I'll find out
What happened so far
- July 2025NextEra vice presidents began signing purchase options with more than 10 landowners for about 800 acres (through January 2026).
Local votes and rules
βΈοΈ Pause on new data centers
County commissioners paused data center applications in January 2026 while staff write zoning rules. They extended the pause three times; on Sept. 2, 2026 they extended it through Dec. 24, 2026. Commissioners have said they do not want a multi-year ban.
An aerial photo of the area.
Where this comes from
- Two data center companies are trying to buy more than 1,000 acres of Sedgwick County land Β· KMUW Β· March 16, 2026
- Sedgwick County extends pause on data center applications through Dec. 24 Β· KWCH 12 Β· Sept 2, 2026