Coffeyville is looking at putting a data center in its industrial park and has received about six proposals. The city says it will study power, water and noise first, which takes about five to six months.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: About six companies sent proposals. City plans a 5-6 month power grid study before choosing.

๐Ÿ•’ Latest update (Aug 31, 2026): City manager said about six companies had sent data center proposals; city plans a Southwest Power Pool study.

What we know

  • ๐Ÿ“ WhereCoffeyville Industrial Park, Coffeyville, Montgomery County

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Aug 31, 2026
    City manager said about six companies had sent data center proposals; city plans a Southwest Power Pool study.

Local votes and rules

๐Ÿ“Œ Other

A motion for a six-month pause on data centers and energy projects died when no commissioner seconded it. Most residents who spoke supported a pause.

July 20, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Coffeyville explores data center at industrial park ยท KOAM ยท Aug 31, 2026