Proximity Park data center and gas plant (Ottawa)
Also called: Lightfield Energy Ottawa
Lightfield Energy planned a data center and a gas power plant on about 300 acres of city land in Ottawa. After almost two years of talks, the city ended the deal in September 2026. A resident ballot measure to ban large data centers is also on the November ballot.
Where things stand: City commission voted 5-0 in September 2026 to end the land sale contract after the developer missed a deadline.
๐ Latest update (Sept 2026): City commission voted 5-0 to end the contract because no development agreement was submitted.
What we know
- ๐ WhereProximity Park, south side of Ottawa (about 300 acres), Ottawa, Franklin County
- ๐ข CompanyLightfield Energy LLC
- ๐ณ Size300 acres
- ๐ Where the power comes fromPlanned natural gas power plant on site.
What happened so far
- Feb 2026City signed a purchase and sale agreement with Lightfield Energy for Proximity Park.
- Sept 2026City commission voted 5-0 to end the contract because no development agreement was submitted.
Local votes and rules
๐ณ๏ธ Public vote
Voters will decide on Nov. 3, 2026 whether to ban data centers that use more than 25 megawatts in Ottawa. The city did not act on the citizen petition (658 valid signatures needed), so residents sued and a judge put it on the ballot.
โ๏ธ Court case
A residents' group sued the city for ignoring its data center petition. On Sept. 3, 2026 the judge ordered the question onto the November ballot, but still has to decide if the petition is legal.
๐ Other
City commissioners voted 5-0 to end the sale of Proximity Park land to Lightfield Energy because the company did not turn in a development agreement in time.
An aerial photo of the area.
Where this comes from
- 'Out of time': Ottawa ends data center contract as ballot fight continues ยท KSHB 41 ยท Sept 2026