Approved, not built yetBig (AI-size): 600 megawatts

CyrusOne data center campus near Waverly (Thayer and Clark roads)

CyrusOne plans six one-story buildings on 280 acres of farmland southwest of Springfield, using up to 600 megawatts. The county approved it in April 2026 after big public debate. Neighbors sued to stop it, but a judge dismissed the lawsuit on Nov. 6, 2026.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Sangamon County Board (for Talkington Township).

Where things stand: Approved, not built yet County Board approved it 17-10 in April 2026. Neighbors sued in July; a judge dismissed the lawsuit on Nov. 6, 2026. They could still appeal.

  • Nov 6, 2026: Sangamon County: lawsuit decided Source

❓ 5 open questions about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Nov 6, 2026): Circuit Judge Adam Giganti dismissed all five claims in the neighbors' lawsuit, with prejudice. He said the County Board had a reasonable basis for approving the data center.

What we know

  • 📍 WhereNorthwest corner of Thayer Road and Clark Road (13000 block of Thayer Road), about 14 miles southwest of Springfield, near Waverly, Talkington, Sangamon County
  • 🏢 CompanyCyrusOne
  • 🌳 Size280 acres
  • ⚡ Power it needs600 megawatts (about as much as 480,000 homes)
  • 🔌 Where the power comes fromRural Electric Convenience Cooperative (RECC) says the current grid has enough power. A 2025 report named Ameren Illinois as the supplier, with CyrusOne paying for power line upgrades.
  • 💧 WaterApple Creek Rural Water system (company says water use is like an office building, mostly restrooms)
  • ❄️ Coolingclosed-loop air cooling (company says it does not use water for cooling)
  • 💵 Cost$500 million
  • 💸 Tax breaksCyrusOne got a 20-year state tax break. Local property taxes on the land would rise from about $20,000-$50,000 a year to an estimated $6.5 million.
  • 👷 Jobs promised100

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which utility will supply the power: Rural Electric Convenience Cooperative or Ameren Illinois? 🙋 I'll find out ·
  • How many diesel backup generators will the site have? 🙋 I'll find out ·
  • Has CyrusOne bought the land and received a building permit? 🙋 I'll find out ·
  • Did local officials sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Will the neighbors appeal the dismissal of their lawsuit? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Oct 2025
      CyrusOne asked the county for a conditional use permit to build on farmland in Talkington Township.
    • March 2026
      County Board voted 15-13 to put off (table) the decision.
    • April 7, 2026
      County Board approved the data center 17-10, with one member not voting.
    • July 6, 2026
      Nearby Waverly residents sued Sangamon County to overturn the approval.
    • Sept 11, 2026
      The county defended its approval in court and asked the judge to dismiss the case.
    • Oct 30, 2026
      Circuit Judge Adam Giganti heard the county's request to dismiss the neighbors' lawsuit. He said he will decide as soon as possible.
    • Nov 6, 2026
      Circuit Judge Adam Giganti dismissed all five claims in the neighbors' lawsuit, with prejudice. He said the County Board had a reasonable basis for approving the data center.

    Local votes and rules

    ⚖️ Court case

    Circuit Judge Adam Giganti dismissed the neighbors' lawsuit against the county's approval of the CyrusOne data center. All five claims were dismissed with prejudice, which means they cannot be filed again in this court. The judge said the county board had a reasonable basis for its decision. The neighbors could still appeal.

    Nov 6, 2026

    ⚖️ Court case

    Neighbors from Waverly and Virden sued the county to undo its approval of the CyrusOne data center. They say the vote broke the county's zoning rules and plan, including noise limits and the use of farmland.

    July 6, 2026

    ✅ Approved

    County board voted 17-10 (one abstained) to approve zoning for CyrusOne's $500 million data center on about 280 acres on Thayer Road near Waverly (Talkington Township). It could use about 600 megawatts. The board had tabled the vote in March.

    April 7, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. First data center in Sangamon County · Illinois Times · Oct 17, 2025
    2. Sangamon County data center vote (tabled proposal) · Springfield Business Journal · March 2026
    3. Sangamon County Board approves a controversial data center project · NPR Illinois · April 7, 2026
    4. Sangamon County, Illinois, Approves $500M Data Center After Heated Debate · Broadband Breakfast · April 10, 2026
    5. Residents sue Sangamon County, CyrusOne · Illinois Times · July 16, 2026
    6. County Board defends data center approval in court · Illinois Times · Sept 22, 2026
    7. CyrusOne Sangamon Data Campus near Waverly, IL (map location) · More Than Just Parks data center tracker · 2026
    8. Judge weighs data center lawsuit's future · Illinois Times · Nov 1, 2026
    9. Judge dismisses data center lawsuit · Illinois Times · Nov 7, 2026
    10. Judge Dismisses Lawsuit Challenging CyrusOne Data Center Approval · Sangamon Reporter · Nov 2026