Monarch Energy 'Rock Air' data center (8685 Friday Road, Rockford)
Also called: Rock Air
Monarch Energy wants to build a 1,400-megawatt data center campus on about 1,300 acres on Rockford's south edge, next to a forest preserve. It says it could invest $12 billion. Neighbors worry about water, power bills and diesel fumes.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Rockford City.
Where things stand: Proposed No site plan or development deal filed with the city yet. The land is already zoned for heavy industry, so a council vote may only be needed if the developer asks for TIF money. A state tax break deal was signed in June 2026.
❓ 4 open questions about it: see below.
Last checked Oct 20, 2026.
🕒 Latest update (Aug 3, 2026): Rockford City Council passed a 6-month data center pause 14-0, but the city says it does not cover this land on Edson Road because an older annexation agreement already allows data centers there.
What we know
- 📍 Where8685 Friday Road, north of Edson Road and south of Kilbuck Creek, near Chicago Rockford International Airport, Rockford, Winnebago County
- 🏢 CompanyMonarch Rock Air LLC (Monarch Energy)
- 🌳 Size1,300 acres
- ⚡ Power it needs1,400 megawatts (about as much as 1,120,000 homes)
- 💸 Tax breaksSigned a state Data Center Investment Program agreement (sales tax break) in June 2026, requiring at least $250 million invested and 100 jobs. Local approval was not needed for that deal.
- 👷 Jobs promised200
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will Monarch build its own power plant on site, and what fuel would it use? 🙋 I'll find out ·
- How much water would the campus use? 🙋 I'll find out ·
- Will the city hold a public hearing before any approval? 🙋 I'll find out ·
- Which company will use the data center? 🙋 I'll find out ·
What happened so far
- March 2026News reports revealed the plan; neighbors and a petition with 2,100+ names raised concerns.
- June 11, 2026State commerce department signed a tax break agreement for a 1,400-megawatt phased data center.
- Aug 3, 2026Rockford City Council passed a 6-month data center pause 14-0, but the city says it does not cover this land on Edson Road because an older annexation agreement already allows data centers there.
Local votes and rules
⏸️ Pause on new data centers
City council voted 14-0 for a 6-month pause on data centers while staff study best practices. The city says the pause does not cover Monarch Energy's land on Edson Road, because an older annexation agreement already allows data centers there.
Drag the slider to compare the land before and now.
Where this comes from
- What happens next on the Rockford data center? · Rock River Current · March 2026
- Neighbors fear destruction if Monarch Energy's data center moves forward in Rockford · WIFR · March 5, 2026
- Incentive deal for proposed Rockford data center shows possible development timeline · Rockford News First / WIFR · July 1, 2026
- City Council approves 6-month data center moratorium, but it doesn't apply to key piece of land · Rock River Current · Aug 3, 2026