Steward Drive data center (Rochelle)

A developer proposed a data center on Steward Drive needing at least 48 megawatts, growing to 150 megawatts later. After public pushback, Rochelle's City Council turned it down unanimously.

✔ ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City Council voted 0-7 against the development agreement on April 27, 2026.

🕒 Latest update (April 27, 2026): City Council voted 0-7 against the data center development agreement.

What we know

  • 📍 WhereAlong Steward Drive, Rochelle, Ogle County
  • 🏢 CompanyMidwest Power Investors LLC (with LFF Industrial)
  • ⚡ Power it needs150 megawatts (about as much as 120,000 homes)

What happened so far

  • March 23, 2026
    City Council put off its vote amid community concern.
  • April 27, 2026
    City Council voted 0-7 against the data center development agreement.

Local votes and rules

✋ Turned down

City council voted 0-7 against a data center deal with Midwest Power Investors along Steward Drive. It would have used 48 megawatts at first, up to 150 later.

April 27, 2026
🛰️ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Rochelle City Council unanimously rejects data center proposal · WIFR · April 28, 2026
  2. Rochelle City Council unanimously denies data center development agreement · Shaw Local (Ogle County News) · April 28, 2026
  3. Rochelle city council delays vote on data center amid community concern · WIFR · March 24, 2026

See something wrong? Tell us and we'll fix it.