Approved, not built yetBig (AI-size): 132 acres

Karis data center campus (Peace and Gurler roads, DeKalb)

Karis proposed seven two-story data center buildings on 132 acres on DeKalb's south side, with a new ComEd substation. The city approved it in 2024, but no user or start date has been announced.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of DeKalb City.

Where things stand: Approved, not built yet City Council approved code changes for the campus in July 2024. No building news since.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (July 22, 2024): City Council held a hearing and approved the plans.

What we know

  • 📍 WhereNortheast corner of Peace Road and Gurler Road, DeKalb's south side, DeKalb, DeKalb County
  • 🏢 CompanyKaris Acquisitions
  • 🌳 Size132 acres
  • 🔌 Where the power comes fromComEd plans a 17.5-acre electrical substation on the site.
  • 🗼 New power linesYes

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the project is at the northeast corner of Peace Road and Gurler Road. The pin is on that corner land.

    What happened so far

    • July 15, 2024
      Planning and Zoning Commission voted unanimously to recommend the plan.
    • July 22, 2024
      City Council held a hearing and approved the plans.

    Local votes and rules

    ✅ Approved

    City council unanimously approved a data center campus by Edged (Endeavour Energy) on about 560 acres in the ChicagoWest Business Center.

    Dec 8, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Proposed DeKalb data center plan gets preliminary OK from panel · Shaw Local (Daily Chronicle) · July 18, 2024
    2. DeKalb OKs plans that could pave way for 2nd data center · Shaw Local (Daily Chronicle) · July 25, 2024
    3. Peace Road / Gurler Road position (intersection ~41.893,-88.724) · OpenStreetMap Nominatim · Oct 8, 2026
    4. Sentinel-2 cloudless 2024 satellite image of the site · EOX / Copernicus Sentinel-2 · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.