Approved, not built yet

Karis data center campus (Peace and Gurler roads, DeKalb)

Karis proposed seven two-story data center buildings on 132 acres on DeKalb's south side, with a new ComEd substation. The city approved it in 2024, but no user or start date has been announced.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: City Council approved code changes for the campus in July 2024. No building news since.

๐Ÿ•’ Latest update (July 22, 2024): City Council held a hearing and approved the plans.

What we know

  • ๐Ÿ“ WhereNortheast corner of Peace Road and Gurler Road, DeKalb's south side, DeKalb, DeKalb County
  • ๐Ÿข CompanyKaris Acquisitions
  • ๐ŸŒณ Size132 acres
  • ๐Ÿ”Œ Where the power comes fromComEd plans a 17.5-acre electrical substation on the site.
  • ๐Ÿ—ผ New power linesYes

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • July 15, 2024
    Planning and Zoning Commission voted unanimously to recommend the plan.
  • July 22, 2024
    City Council held a hearing and approved the plans.

Local votes and rules

โœ… Approved

City council unanimously approved a data center campus by Edged (Endeavour Energy) on about 560 acres in the ChicagoWest Business Center.

Dec 8, 2025
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Proposed DeKalb data center plan gets preliminary OK from panel ยท Shaw Local (Daily Chronicle) ยท July 18, 2024
  2. DeKalb OKs plans that could pave way for 2nd data center ยท Shaw Local (Daily Chronicle) ยท July 25, 2024

See something wrong? Tell us and we'll fix it.