Aligned Data Centers campus (Reed and Carbon Hill roads, Coal City)
Aligned Data Centers wants to build a large data center campus on about 320 acres in Coal City's industrial park. More than 1,000 residents have opposed it. The Village Board will make the final decision after hearings.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Village Board of Coal City Village.
Where things stand: Proposed Aligned filed a planned development and an annexation request in July 2026. A review committee and public hearings come before the Village Board's final vote.
❓ 4 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (July 20, 2026): Aligned filed plans to annex one parcel from Braceville Township and rezone it for industry, plus a planned development for the campus.
What we know
- 📍 WhereSoutheast corner of East Reed Road and South Carbon Hill Road, Coal City, Grundy County
- 🏢 CompanyAligned Data Centers
- 🌳 Size320 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts would the campus use? 🙋 I'll find out ·
- How much water would it use per day, and from where? 🙋 I'll find out ·
- When is the Village Board's public hearing and vote? 🙋 I'll find out ·
- Did village officials sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: the project is at the southeast corner of East Reed Road and South Carbon Hill Road. The pin is on that corner land.
What happened so far
- 2026Village Board added members to a review committee for the plan; many residents spoke against it.
- July 20, 2026Aligned filed plans to annex one parcel from Braceville Township and rezone it for industry, plus a planned development for the campus.
Drag the slider to compare the land before and now.
Where this comes from
- ADC Coal City IL - Village Annexation Narrative · Village of Coal City · July 20, 2026
- Data Center · Village of Coal City · 2026
- Coal City officials release Aligned data center planned unit development proposal · WCSJ / WSPY News · 2026
- Coal City board holds public hearing for possible annexation · WCSJ / WSPY News · 2026