PathOne data center at former Bison plant (near Hull)
PathOne and Sunstone Investments want to reuse an old renewable fuel plant near Hull for a small data center, starting at about 10 MW. They ask the county to cap the site at 25 MW. Sioux County paused data centers for a year in June 2026, then passed new rules with a size limit in October 2026.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Sioux County Board of Supervisors (for land outside city and town limits).
Where things stand: Proposed Sioux County supervisors passed new data center rules on Oct. 27, 2026, 4-1. The county's one-year moratorium dates from June 2026; we have not confirmed whether it has ended.
- Oct 27, 2026: Unincorporated Sioux County, Sioux County: data center rules (ordinance) adopted Source
❓ 4 open questions about it: see below.
Last checked Nov 2, 2026.
🕒 Latest update (Oct 27, 2026): Sioux County supervisors voted 4-1 to pass the third and final reading of the data center rules. The vote was on the rules, not on any data center.
What we know
- 📍 WhereFormer Bison Renewable Energy property off Highway 75, about 2 miles southwest of Hull, Unincorporated Sioux County, Sioux County
- 🏢 CompanyPathOne Data Centers and Sunstone Investments
- ⚡ Power it needs10 megawatts (about as much as 8,000 homes)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the customer for this data center? 🙋 I'll find out ·
- Will the county's new ordinance allow it? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
- Has Sioux County's one-year moratorium ended now that the new rules have passed? 🙋 I'll find out ·
What happened so far
- June 16, 2026Sioux County passed a one-year moratorium on data centers and battery storage.
- June 30, 2026Developers said they had a customer lined up before the moratorium.
- Aug 25, 2026PathOne held a public meeting for Hull residents.
- Sept 29, 2026Sioux County supervisors approved the first reading of new data center rules for rural areas, including a 25-megawatt size limit, closed-loop cooling and no private wells for cooling.
- Oct 13, 2026Sioux County supervisors passed the second reading of the data center rules 4-1. The rules make developers pay for substation upgrades and let the county shut down a data center that breaks its power or water limits.
- Oct 27, 2026Sioux County supervisors voted 4-1 to pass the third and final reading of the data center rules. The vote was on the rules, not on any data center.
Local votes and rules
📜 Data center rules
Supervisors passed the county's data center rules on the final reading, 4-1. Each site is limited to 25 megawatts, and a formula limits how many data centers can be built. The rules cover water, power and noise. They take effect when published on Nov. 4, 2026.
⏸️ Pause on new data centers
Right after passing the new data center rules, supervisors voted 4-1 to end the county's one-year pause on data centers, months before its planned end in June 2027.
📜 Data center rules
Supervisors approved the first of three readings of new rules for data centers in rural areas. Second reading Oct. 13, final reading planned Oct. 27, 2026.
⏸️ Pause on new data centers
Supervisors approved a one-year pause on new data centers and big battery storage sites in the countryside. Cities keep their own zoning. The county may write rules like its wind and solar rules. A planned data center near Hull is on hold.
Drag the slider to compare the land before and now.
Where this comes from
- 'Not ideal for our project'- Data center developers confirm buyer was in place before Sioux County moratorium · Dakota News Now · June 30, 2026
- After Ida County, PathOne holds data center meeting for Hull residents · KTIV · Aug 26, 2026
- Sioux County proposes new ordinance to regulate data centers · KTIV / Dakota News Now · Sept 30, 2026
- Sioux County data center ordinance moves to final step · N'West Iowa Review · Oct 19, 2026
- Sioux County approves strict new rules for future data centers · KTIV · Oct 27, 2026
See something wrong? Tell us and we'll fix it.