ProposedBig (AI-size): 545 acres

Google data center campus near Duane Arnold nuclear plant (Palo area)

Also called: Project Meridian

Google wants to build up to six data center buildings on about 545 acres next to the Duane Arnold nuclear plant near Palo. The plant is being restarted to sell power to Google. Linn County has paused new big data centers, so the plan may depend on Palo annexing the land.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Monday, November 30, 2026 (time not announced)

Palo Planning & Zoning Commission meeting

📍 Palo

Date from a news report; no official agenda seen yet.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Proposed Google formally asked Palo to annex the land in November 2026. Palo's Planning & Zoning Commission will review the request on Nov. 30, 2026; then it goes to the City Council.

❓ 4 open questions about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Nov 3, 2026): A Google water memo sent to Palo says the campus could use up to 10.4 million gallons of Cedar River water a day at full size; early phases would use less.

What we know

  • 📍 WhereFarmland next to the Duane Arnold Energy Center, outside Palo, Unincorporated Linn County, Linn County
  • 🏢 CompanyGoogle
  • 🏛️ Owned byAlphabet
  • 👤 Built forGoogle
  • 🌳 Size545 acres
  • 🔌 Where the power comes fromDuane Arnold nuclear plant restart (NextEra), under a 25-year power deal with Google
  • 💧 WaterCedar River (reported) · 10,400,000 gallons a day

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did Palo officials sign an agreement with Google to keep the plans private (NDA)? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
  • How big is the site? Reports say about 550 acres (The Gazette) or about 650 acres plus 100 acres to connect to the city (Iowa Public Radio, Radio Iowa). 🙋 I'll find out ·
  • When will the Palo City Council vote on Google's annexation and rezoning request? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 2025
      Google first approached Linn County about the project.
    • Oct 2025
      Google and NextEra announced a 25-year deal to buy power from the restarted Duane Arnold nuclear plant.
    • Feb 2026
      Linn County passed a data center zoning ordinance.
    • March 4, 2026
      Linn County said Google dropped its county plan and would seek to build inside Palo instead. Google had said it would need about 12 million gallons of Cedar River water a day.
    • July 20, 2026
      Palo City Council passed its data center ordinance 4-1. This does not approve the Google project or an annexation.
    • Aug 10, 2026
      Linn County supervisors declined to allow large data centers next to nuclear plants during its 18-month moratorium.
    • Oct 9, 2026
      Google mailed a letter to Palo residents about its proposed 545-acre data center campus and invited them to an open house on Oct. 22. Google says it plans to ask Palo to annex the land.
    • Oct 22, 2026
      Google held a public open house at the Palo Community Center. It said it hopes the campus will run by the end of 2028, will take cooling water from the Cedar River and not from bedrock aquifers, and estimates $170 million in taxes over 20 years.
    • Nov 2026
      Google formally petitioned Palo to annex about 650 acres of Linn County land: about 550 acres for the data center and about 100 acres of farm buffer to connect it to the city. The city posted a notice about the application.
    • Nov 3, 2026
      A Google water memo sent to Palo says the campus could use up to 10.4 million gallons of Cedar River water a day at full size; early phases would use less.

    Local votes and rules

    📌 Other

    Supervisors decided not to change the county's EU-2 zoning district, which would have let big data centers locate near the Duane Arnold nuclear plant near Palo before the county's pause ends. A supervisor said there was not broad public support.

    Aug 10, 2026

    📜 Data center rules

    Palo's council voted 4-1 on the final reading of Ordinance 93-2026. It creates a special zoning district (EU-1) for data centers, with setbacks, noise and traffic rules. It does not approve any project; Google is still looking at land near Palo. Most people at the meetings spoke against it.

    July 20, 2026

    ⏸️ Pause on new data centers

    Supervisors voted 2-1 to stop taking new requests to rezone land into the county's data center district for 18 months, even though the county passed data center rules in February. Cities like Cedar Rapids and Palo are not covered.

    July 1, 2026

    📜 Data center rules

    Supervisors voted unanimously to make a new zoning district just for big data centers in the countryside. Builders must stay 1,000 feet from homes zoned residential, study their water use, sign a water deal with the county, limit noise and light, pay for road damage, and hold a public meeting first. It does not apply inside Cedar Rapids or other cities.

    Feb 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something