Edged data center campus (Council Bluffs)
Also called: Project Lola, EDC Omaha Landco LLC, OMA01
Edged is building two data center buildings in Council Bluffs, about 200 MW in total. The city approved a smaller, lower design than first asked for. Building frames were finished in 2026.
Where things stand: Two buildings reached 'topping out' by September 2026.
π Latest update (Sept 2026): Edged said both buildings were topped out.
What we know
- π WhereNear College Road and East Kanesville Boulevard, Council Bluffs, Pottawattamie County
- π’ CompanyEdged (EDC Omaha Landco LLC)
- ποΈ Owned byEdged US (backed by Koch Real Estate Investments)
- β‘ Power it needs200 megawatts (about as much as 160,000 homes)
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water and power will the campus use? π I'll find out
- When will it open? π I'll find out
What happened so far
- 2025Council Bluffs approved a smaller plan: two buildings of about 285,000 sq ft each, about 36 feet tall.
- Oct 2025Edged broke ground.
- Sept 2026Edged said both buildings were topped out.
Local votes and rules
βΈοΈ Pause on new data centers
Council Bluffs's council unanimously voted down the mayor's request for a one-year pause on new data centers. The mayor wanted time to update city data center rules from 2007, and said water and sewer systems are near capacity. Projects already underway would not have been affected.
An aerial photo of the area.
Where this comes from
- Edged Completes Construction Of Data Centers In Council Bluffs, Iowa Β· Baxtel Β· Sept 14, 2026