QTS data center campus at Big Cedar Industrial Center (Cedar Rapids)
QTS is building a large data center campus on 612 acres in southwest Cedar Rapids. QTS calls it a $10 billion project, the biggest in the city's history. The city deal allows up to seven buildings.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Cedar Rapids City.
Where things stand: Being built First three buildings were topped out in October 2025. The city allows up to seven phases.
❓ 2 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (Dec 2, 2025): City Council unanimously approved changes to the deal: up to seven phases, each at least a 300,000 sq ft building.
What we know
- 📍 Where6200 76th Ave SW, Big Cedar Industrial Center, southwest Cedar Rapids, Cedar Rapids, Linn County
- 🏢 CompanyQTS Data Centers
- 🌳 Size612 acres
- 🔌 Where the power comes fromAlliant Energy
- ❄️ Coolingwater-free cooling system (company says)
- 💵 Cost$10 billion
- 💸 Tax breaksCity deal includes a 20-year, 75% rebate of Alliant franchise fees and rebates of 70% of new property tax (tax increment financing). QTS pays $300,000 per phase into a community fund.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much electricity will the full campus use? Reports range from about 1,000 MW to more. 🙋 I'll find out ·
- How much water will the campus use per day once all buildings run? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: Linn County land records list 13 parcels (about 630 acres) owned by QTS Cedar Rapids companies along 76th Avenue SW, including parcels named for data center buildings DC1 to DC7. The pin is on the DC2 parcel at 6200 76th Ave SW, next to DC1 and DC3, the first three buildings.
What happened so far
- Jan 2025Cedar Rapids approved the QTS development deal for Big Cedar Industrial Park.
- Oct 21, 2025Officials held a 'topping out' ceremony for the first three buildings.
- Dec 2, 2025City Council unanimously approved changes to the deal: up to seven phases, each at least a 300,000 sq ft building.
Local votes and rules
🤝 Agreement with the company
Cedar Rapids's council unanimously changed its deal with QTS: up to seven phases, each with a building of at least 300,000 square feet and about $250 million. QTS pays $300,000 per phase into a community fund.
Drag the slider to compare the land before and now.
Where this comes from
- Cedar Rapids, Iowa Gets Approval for Two Major Data Center Investments by Google and QTS · Data Center Frontier
- Officials hold topping out ceremony for $10 billion Cedar Rapids data center campus · KCRG · Oct 22, 2025
- Cedar Rapids approves changes to $1.75 billion data center complex agreement · CBS2 Iowa · Dec 2, 2025
- Iowa communities grapple with regulating data centers as development spreads · Business Record · Sept 11, 2026
- Cedar Rapids Assessor: parcel 201540100200000, 6200 76th Ave Unit 200, owner QTS Cedar Rapids I DC2 LLC · Cedar Rapids City Assessor · Oct 8, 2026
- Linn County Real Estate Parcel layer: parcels owned by QTS Cedar Rapids LLCs · Linn County, Iowa · Oct 8, 2026
- USGS imagery of the site · USGS The National Map · Oct 8, 2026