USA โ€บ Iowa โ€บ Linn County โ€บ Cedar Rapids City
Approved, not built yet

Oppidan data center at 1515 33rd Ave. SW (Cedar Rapids)

Also called: CLOP Cedar Rapids IA LLC

A Minnesota developer, Oppidan, has a city building permit for a data center of about 98,000 square feet on 33rd Avenue SW. The land was already zoned for light industry. The project is valued at about $101.5 million.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City issued a building permit on June 22, 2026. Start of construction not confirmed.

๐Ÿ•’ Latest update (July 8, 2026): City confirmed a third data center is planned on the southwest side.

What we know

  • ๐Ÿ“ Where1515 33rd Ave. SW, north of Highway 30 and west of I-380, Cedar Rapids, Linn County
  • ๐Ÿข CompanyCLOP Cedar Rapids IA LLC
  • ๐Ÿ›๏ธ Owned byOppidan
  • ๐Ÿ’ต Cost$102 million
  • ๐Ÿ’ธ Tax breaksCity says no city incentives.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 22, 2026
    City issued a building permit for a 98,000 sq ft data center.
  • July 8, 2026
    City confirmed a third data center is planned on the southwest side.

Local votes and rules

๐Ÿค Agreement with the company

Cedar Rapids's council unanimously changed its deal with QTS: up to seven phases, each with a building of at least 300,000 square feet and about $250 million. QTS pays $300,000 per phase into a community fund.

Dec 2025
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Building permits filed for third data center project in Cedar Rapids ยท CBS2 Iowa ยท 2026
  2. Cedar Rapids confirms third data center planned for southwest side ยท KCRG ยท July 8, 2026

See something wrong? Tell us and we'll fix it.