Being built

Edged data center (Ankeny)

Also called: Edged Des Moines LLC

Edged is building a 105,000 sq ft data center on 17.5 acres on Ankeny's southeast side. It starts at 13.2 MW and costs about $187 million. The company says its closed-loop cooling uses little to no water.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Ankeny City.

Where things stand: Being built Approved March 2025; construction was planned from 2025 to the end of 2026.

❓ 1 open question about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (March 3, 2025): Ankeny City Council approved a development agreement for a 105,000 sq ft multi-tenant data center.

What we know

  • 📍 Where9100 SE Four Mile Dr (Lot 1, I-80 Commerce Center Plat 1), Ankeny, just north of I-80, Ankeny, Polk County
  • 🏢 CompanyEdged Des Moines LLC
  • 🏛️ Owned byEdged
  • 🌳 Size17.5 acres
  • ⚡ Power it needs13.2 megawatts (about as much as 10,560 homes)
  • ❄️ Coolingclosed-loop water and glycol system (company says little to no water)
  • 💵 Cost$187 million
  • 💸 Tax breaksFive-year tax increment financing package, up to $2 million.
  • 👷 Jobs promised22

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the Polk County Assessor lists 9100 SE Four Mile Drive, Ankeny (14.6 acres) as owned by Edged Des Moines LLC, with a 102,208 sq ft "Computer Data Center" building on the 2026 tax roll.

    What happened so far

    • March 3, 2025
      Ankeny City Council approved a development agreement for a 105,000 sq ft multi-tenant data center.

    Local votes and rules

    🤝 Agreement with the company

    Ankeny's council approved a development deal with Edged for a 105,000-square-foot data center on 17.5 acres. The city gives up to $2 million in tax-increment help over five years; Edged pays to extend water and sewer and promises 22 jobs.

    March 3, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Ankeny council approves data center development agreement · Business Record · March 2025
    2. Polk County Assessor: parcel 181/42318-226-002, 9100 SE Four Mile Dr, owner Edged Des Moines LLC · Polk County Assessor · Oct 8, 2026
    3. Edged tops out data center in Des Moines, Iowa (9100 SE Four Mile Drive) · DatacenterDynamics · 2025
    4. USGS imagery of the site · USGS The National Map · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.