Being built
Servpac MTP Data Center Building 2 (Mililani Technology Park)
Also called: MTP Data Center Phase 2, MTP Data Center expansion
A Hawaii company, Servpac, is building a second building at its data center in Mililani. It adds 15,500 square feet and costs $13 million. It is small compared with the giant data centers being built on the mainland.
Where things stand: Servpac broke ground in January 2026 and said it would be done in spring 2026 (Q2). We found no news yet that it is finished.
๐ Latest update (March 9, 2026): Building Industry Hawaii reported the groundbreaking; finish expected in Q2 2026.
What we know
- ๐ WhereMililani Technology Park, next to Servpac's existing data center at 200 Kahelu Ave, Mililani (the new building is on 5 more acres of company land nearby), Honolulu County, Honolulu County
- ๐ข CompanyServpac Inc.
- ๐ค Built forServpac customers (local cloud and server rental)
- ๐ณ Size5 acres
- ๐ Where the power comes fromHawaiian Electric's Oahu grid, plus its own backup power and large on-site solar panels, the company says.
- ๐ต Cost$13 million
- ๐ท Jobs promised15
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much electricity will Building 2 use (in megawatts)? ๐ I'll find out
- Is Building 2 finished and running yet? ๐ I'll find out
- How many diesel backup generators will it have? ๐ I'll find out
What happened so far
- June 2023Servpac started a first expansion inside its Mililani data center to double the space it rents out.
- Jan 22, 2026Servpac broke ground on Building 2, a $13 million, 15,500-square-foot addition.
- March 9, 2026Building Industry Hawaii reported the groundbreaking; finish expected in Q2 2026.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.
Where this comes from
- MTP Phase 2 Groundbreaking Ceremony ยท Servpac ยท Jan 22, 2026
- Servpac Inc. breaks ground on MTP Data Center's Building 2 ยท Building Industry Hawaii ยท March 9, 2026
- MTP Data Center Tier IV expansion ยท Servpac ยท 2023
- MTP Data Center (address 200 Kahelu Ave, Mililani) ยท Data Center Map
- Census geocoder: 200 Kahelu Ave, Mililani ยท U.S. Census Bureau ยท Oct 8, 2026