Stopped or cancelled
Sentinel Grove Technology Park (western St. Lucie County)
Also called: Project Jarvis
A developer proposed up to 15 million square feet of data center buildings on about 1,200 acres of farmland west of Fort Pierce. The county planning board voted against it, and the developer pulled back in early 2026.
Where things stand: County planning board voted against it in October 2025. The developer pulled back in early 2026.
๐ Latest update (Feb 2026): A county commissioner said the developer appeared to pull back while waiting on new state data center laws.
What we know
- ๐ WhereFarmland west of Fort Pierce, along Orange Avenue, Unincorporated St. Lucie County, St. Lucie County
- ๐ณ Size1,218 acres
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Was the application formally withdrawn, or only paused? ๐ I'll find out
- Who was the developer and end user? ๐ I'll find out
What happened so far
- Oct 16, 2025County Planning and Zoning board voted 4-2 against recommending the land-use change for the project.
- Feb 2026A county commissioner said the developer appeared to pull back while waiting on new state data center laws.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- St. Lucie County planning board votes against billion-dollar data center proposal in Fort Pierce ยท WQCS ยท Oct 17, 2025
- SCRAPPED? Developer of St. Lucie County data center project may withdraw plan amid new AI legislation ยท WFLX ยท Feb 23, 2026