Being built

HostDime flagship data center (Eatonville)

HostDime is finishing a seven-story, 100,000 square foot data center on a former school site in Eatonville. It is more than a year late, and the town has fined it over $99,000.

✔ ConfirmedSourceLast checked: Oct 2026

Where things stand: Nearly done but over a year late. The town fines HostDime $250 a day; it planned to open in September 2026.

🕒 Latest update (Sept 1, 2026): Town Council put off a vote on doubling the daily fine until it meets with HostDime. Fines so far: $99,250.

What we know

  • 📍 Where1000 Wymore Road, east of Interstate 4, on part of the former Hungerford school land, Eatonville, Orange County
  • 🏢 CompanyHostDime
  • 👤 Built forHostDime (rents space to customers)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

🔎 What we checked

  • Oct 8, 2026: We checked aerial photos: a tall building under construction stands on Wymore Road next to Interstate 4, on the former school land.

What happened so far

  • July 2025
    HostDime missed its deadline to open; the town began fining it $250 a day.
  • Sept 1, 2026
    Town Council put off a vote on doubling the daily fine until it meets with HostDime. Fines so far: $99,250.

Local votes and rules

📌 Other

The town has fined HostDime $250 a day since July 2025 for missing its deadline to open its data center. The council put off a vote on doubling the fine until it meets with the company.

Sept 1, 2026
🛰️ See it from above

Drag the slider to compare the land before and now.

20182025