AI upgrade of the old Nasdaq data center, 80 Merritt Blvd
Also called: Trumbull Data Center, AC Trumbull LLC, 365 Data Centers Trumbull
An older data center at 80 Merritt Boulevard may be upgraded into one of Connecticut's first AI data centers, a $200 million project. The town says the owners agreed not to raise power draw, noise or water use, or to make the building bigger. Residents asked for a pause and the town passed one for new data centers only.
Where things stand: Existing data center; owners plan to turn it into an AI data center. Town's new 2-year moratorium does not cover this existing building.
π Latest update (Sept 9, 2026): Trumbull approved a 2-year moratorium on new data centers. It does not cover upgrades to this existing building.
What we know
- π Where80 Merritt Boulevard, Trumbull Corporate Park, Trumbull, Greater Bridgeport Planning Region
- π’ CompanyAC Trumbull LLC (Aphorio Carter Critical Infrastructure Fund and CogNOVUM)
- ποΈ Owned byCarter Funds
- π€ Built for365 Data Centers (evaluating)
- π³ Size8.4 acres
- β‘ Power it needs15 megawatts (about as much as 12,000 homes)
- π Where the power comes fromExisting grid connection, about 15 megawatts today.
- π΅ Cost$200 million
- πΈ Tax breaksHost fee agreement with the town lets the owners get state sales and use tax breaks under the state data center program.
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How will the town enforce the promise of no more power, noise or water use? π I'll find out
- Will the owners release the letter of intent with 365 Data Centers? π I'll find out
- How many megawatts will the upgraded site use? π I'll find out
What happened so far
- 2024Aphorio Carter's fund bought the former Nasdaq and Digital Realty data center for $10 million.
- 2025Trumbull's Rules and Research Committee approved a resolution letting the First Selectman sign a host fee agreement with AC Trumbull LLC and CogNOVUM.
- May 6, 2026365 Data Centers and Aphorio Carter announced a partnership and named Trumbull as a possible AI data center site.
- June 26, 2026Residents delivered a petition to the Town Council asking for a joint meeting and a pause on AI data centers.
- Sept 9, 2026Trumbull approved a 2-year moratorium on new data centers. It does not cover upgrades to this existing building.
Local votes and rules
βΈοΈ Pause on new data centers
The Town Council approved a 2-year pause on new data centers. It does not cover the planned AI upgrade of the existing data center at 80 Merritt Boulevard, even though residents asked for that.
π€ Agreement with the company
A Town Council committee approved letting the First Selectman sign a host fee agreement with the owners of the 80 Merritt Boulevard data center. The exact date is not public in the sources we found.
Drag the slider to compare the land before and now.
Where this comes from
- Proposed Trumbull AI data center at Nasdaq site worrisome to residents Β· Westfair Communications Β· July 19, 2026
- 365 Data Centers eyes CT for AI data center as part of national expansion Β· Hartford Business Journal Β· May 6, 2026
- Trumbull could become home to one of CT's first AI data centers despite new 2-year moratorium Β· CT Mirror / Connecticut Public Β· Sept 11, 2026