Proposed
Atlas Capital data center on Griffin Road North
Also called: Atlas Capital Group Bloomfield
A New York company showed Bloomfield an early plan for a very large data center on empty land on Griffin Road North. It would have its own power substation and backup generators. No formal application has been reported.
Where things stand: Only an informal concept shown to the Planning and Zoning Commission in June 2025. No formal application found.
๐ Latest update (June 26, 2025): Atlas Capital showed a concept plan to Bloomfield's Planning and Zoning Commission: a 2-story, more than 1 million square foot data center with a 127,000 square foot substation.
What we know
- ๐ Where132 Griffin Road North, off Route 189 (former tobacco field), Bloomfield, Capitol Planning Region
- ๐ข CompanyAtlas Capital Group
- ๐ณ Size44.5 acres
- ๐ Where the power comes fromEversource grid; plan shows a large open-air substation. Backup generator yards planned.
- โ๏ธ CoolingChillers on the roof
- ๐ท Jobs promised40
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has Atlas Capital filed a formal application with Bloomfield? ๐ I'll find out
- How many megawatts would it use, and who would pay for grid upgrades? ๐ I'll find out
- Who would use the data center? ๐ I'll find out
What happened so far
- June 26, 2025Atlas Capital showed a concept plan to Bloomfield's Planning and Zoning Commission: a 2-story, more than 1 million square foot data center with a 127,000 square foot substation.
๐ฐ๏ธ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- NY developer proposes 1M-sq.-ft. data center in Connecticut ยท Hartford Business Journal ยท July 2, 2025
- Connecticut Data Center Proposed Projects (2026 Summary) ยท Energize Connecticut ยท Aug 11, 2026