USA โ€บ Colorado โ€บ Arapahoe County โ€บ Aurora City
Being built

QTS Aurora-Denver data center campus

Also called: QTS Denver DC1-DC3, QTS DEN1

QTS is building a three-building data center campus on about 65 acres on the east side of Aurora. It will need at least 160 megawatts, making it the biggest data center in Colorado today. QTS wants to have 138 diesel backup generators there, and the state is reviewing that air permit.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: One building done, a second nearly done and a third site being prepared (CPR, July 2026). A state air permit for more generators is under review.

๐Ÿ•’ Latest update (July 8, 2026): CPR reported one building done, a second nearly done and work starting on a third; state regulators said they would look into air-rule compliance.

What we know

  • ๐Ÿ“ Where1160 N Gun Club Rd, Aurora, south of Denver International Airport, Aurora, Arapahoe County
  • ๐Ÿข CompanyQTS Data Centers
  • ๐ŸŒณ Size65 acres
  • โšก Power it needs160 megawatts (about as much as 128,000 homes)
  • ๐Ÿ’ง WaterAurora Water ยท 2,400 gallons a day
  • โ„๏ธ Coolingclosed-loop (not evaporative) cooling
  • ๐Ÿ›ข๏ธ Diesel generators138

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Feb 2025
    QTS got local construction permits from Aurora.
  • July 2025
    QTS asked state air regulators to change its permit to add 98 diesel generators to the 40 already there.
  • July 8, 2026
    CPR reported one building done, a second nearly done and work starting on a third; state regulators said they would look into air-rule compliance.

Local votes and rules

๐Ÿ“œ Data center rules

Aurora City Council banned water-heavy evaporative cooling in new commercial, apartment and industrial buildings, including data centers. It does not apply to the city's existing data centers. Rules on setbacks, noise and screening are still being written.

Sept 2026

๐Ÿ“Œ Other

Aurora City Council rejected a pause on new data centers; the mayor broke a tie. Instead it voted 7-4 to write data center rules, starting with a ban on water-heavy evaporative cooling and setbacks and buffers near some mixed-use areas.

Aug 10, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. QTS Aurora data center plans 98 more diesel generators ยท Colorado Public Radio ยท July 8, 2026
  2. Local governments in Colorado enact moratoriums on data center development ยท KUNC / Colorado Newsline ยท Aug 10, 2026
  3. QTS Aurora-Denver Campus listing (1160 N Gun Club Rd) ยท ocolo.io ยท 2026

See something wrong? Tell us and we'll fix it.