Being built
DataBank / Goodman data center in Vernon
Goodman and DataBank are finishing a 32-megawatt data center in Vernon, an industrial city next to Los Angeles. The first part should open in December 2026 and the rest in steps through September 2027.
Where things stand: First 6 MW expected to open December 2026; the rest by September 2027.
๐ Latest update (April 9, 2026): DataBank and Goodman announced a joint venture to open the Vernon data center, first 6 MW in December 2026.
What we know
- ๐ WhereVernon, Los Angeles County
- ๐ข CompanyGoodman Group and DataBank (joint venture)
- โก Power it needs32 megawatts (about as much as 25,600 homes)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- What is the street address? ๐ I'll find out
- How many diesel backup generators will it have? ๐ I'll find out
What happened so far
- April 9, 2026DataBank and Goodman announced a joint venture to open the Vernon data center, first 6 MW in December 2026.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- DataBank and Goodman Group partner to open new landmark data center in Los Angeles ยท IREI ยท April 9, 2026
See something wrong? Tell us and we'll fix it.