Project Midway data center campus southwest of Casa Grande

Also called: Project Midway

IDM Companies wants to build a data center campus on about 216 acres of rural land southwest of Casa Grande, next to a planned gas power plant. The county changed its land-use plan in 2025, but the rezoning has not been decided.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: County approved a land-use plan change in November 2025. The rezoning (case PZ-008-26) went to the Planning Commission in July 2026 and was put off to a later date.

πŸ•’ Latest update (July 16, 2026): Planning Commission heard the rezoning to industrial and voted to continue it to a later date, citing questions such as who the end user is.

What we know

  • πŸ“ WhereAbout 216 acres at the southwest corner of Selma Highway and Midway Road, southwest of Casa Grande and east of Stanfield, Unincorporated Pinal County, Pinal County
  • 🏒 CompanyIDM Companies
  • 🌳 Size216 acres
  • πŸ”Œ Where the power comes fromNext to Project Bella, a planned 480-megawatt gas and battery power plant; the developer points to nearby power lines.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • July 17, 2025
    County Planning Commission discussed the plan in a work session.
  • Nov 19, 2025
    County supervisors approved the land-use plan change from homes to employment.
  • July 16, 2026
    Planning Commission heard the rezoning to industrial and voted to continue it to a later date, citing questions such as who the end user is.

Local votes and rules

πŸ“Œ Other

The county planning commission heard the request to rezone about 216 acres to industrial for the Project Midway data center campus and put off its vote to a later date, with questions such as who the end user is.

July 16, 2026

πŸ—ΊοΈ Zoning change

County supervisors unanimously approved land-use plan changes for three big data center sites: La Osa near Eloy, Project Midway southwest of Casa Grande, and the W Holdings energy and tech campus south of Maricopa. These plan changes do not rezone the land; each site still needs a rezoning vote.

Nov 19, 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Pinal considering 215-acre data center development Β· AZBEX Β· July 2025
  2. Pinal County data center projects update Β· Rose Law Group Reporter Β· April 2026
  3. Pinal data center cases Β· AZBEX Β· 2026
  4. Pinal County Planning & Zoning Commission meeting, July 16, 2026 Β· Govly (meeting summary) Β· July 16, 2026
  5. Data center OK'd Β· InMaricopa Β· Nov 20, 2025
  6. OpenStreetMap: Midway Road meets Selma Highway Β· OpenStreetMap Nominatim Β· Oct 7, 2026

See something wrong? Tell us and we'll fix it.