ProposedBig (AI-size): 216 acres

Project Midway data center campus southwest of Casa Grande

Also called: Project Midway

IDM Companies wants to build a data center campus on about 216 acres of rural land southwest of Casa Grande, next to a planned gas power plant. The county changed its land-use plan in 2025, but the rezoning has not been decided.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Pinal County Board of Supervisors (for land outside city and town limits).

Where things stand: Proposed County approved a land-use plan change in November 2025. The rezoning (case PZ-008-26) went to the Planning Commission in July 2026 and was put off to a later date.

❓ 4 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 16, 2026): Planning Commission heard the rezoning to industrial and voted to continue it to a later date, citing questions such as who the end user is.

What we know

  • 📍 WhereAbout 216 acres at the southwest corner of Selma Highway and Midway Road, southwest of Casa Grande and east of Stanfield, Unincorporated Pinal County, Pinal County
  • 🏢 CompanyIDM Companies
  • 🌳 Size216 acres
  • 🔌 Where the power comes fromNext to Project Bella, a planned 480-megawatt gas and battery power plant; the developer points to nearby power lines.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who would use the data center? 🙋 I'll find out ·
  • When will the Planning Commission take up the rezoning again? 🙋 I'll find out ·
  • How much power and water would it use? 🙋 I'll find out ·
  • Would it buy power from the planned Project Bella gas plant next door? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 17, 2025
      County Planning Commission discussed the plan in a work session.
    • Nov 19, 2025
      County supervisors approved the land-use plan change from homes to employment.
    • July 16, 2026
      Planning Commission heard the rezoning to industrial and voted to continue it to a later date, citing questions such as who the end user is.

    Local votes and rules

    📌 Other

    The county planning commission heard the request to rezone about 216 acres to industrial for the Project Midway data center campus and put off its vote to a later date, with questions such as who the end user is.

    July 16, 2026

    🗺️ Zoning change

    County supervisors unanimously approved land-use plan changes for three big data center sites: La Osa near Eloy, Project Midway southwest of Casa Grande, and the W Holdings energy and tech campus south of Maricopa. These plan changes do not rezone the land; each site still needs a rezoning vote.

    Nov 19, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Pinal considering 215-acre data center development · AZBEX · July 2025
    2. Pinal County data center projects update · Rose Law Group Reporter · April 2026
    3. Pinal data center cases · AZBEX · 2026
    4. Pinal County Planning & Zoning Commission meeting, July 16, 2026 · Govly (meeting summary) · July 16, 2026
    5. Data center OK'd · InMaricopa · Nov 20, 2025
    6. OpenStreetMap: Midway Road meets Selma Highway · OpenStreetMap Nominatim · Oct 7, 2026