Project Midway data center campus southwest of Casa Grande
Also called: Project Midway
IDM Companies wants to build a data center campus on about 216 acres of rural land southwest of Casa Grande, next to a planned gas power plant. The county changed its land-use plan in 2025, but the rezoning has not been decided.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Pinal County Board of Supervisors (for land outside city and town limits).
Where things stand: Proposed County approved a land-use plan change in November 2025. The rezoning (case PZ-008-26) went to the Planning Commission in July 2026 and was put off to a later date.
❓ 4 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (July 16, 2026): Planning Commission heard the rezoning to industrial and voted to continue it to a later date, citing questions such as who the end user is.
What we know
- 📍 WhereAbout 216 acres at the southwest corner of Selma Highway and Midway Road, southwest of Casa Grande and east of Stanfield, Unincorporated Pinal County, Pinal County
- 🏢 CompanyIDM Companies
- 🌳 Size216 acres
- 🔌 Where the power comes fromNext to Project Bella, a planned 480-megawatt gas and battery power plant; the developer points to nearby power lines.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who would use the data center? 🙋 I'll find out ·
- When will the Planning Commission take up the rezoning again? 🙋 I'll find out ·
- How much power and water would it use? 🙋 I'll find out ·
- Would it buy power from the planned Project Bella gas plant next door? 🙋 I'll find out ·
What happened so far
- July 17, 2025County Planning Commission discussed the plan in a work session.
- Nov 19, 2025County supervisors approved the land-use plan change from homes to employment.
- July 16, 2026Planning Commission heard the rezoning to industrial and voted to continue it to a later date, citing questions such as who the end user is.
Local votes and rules
📌 Other
The county planning commission heard the request to rezone about 216 acres to industrial for the Project Midway data center campus and put off its vote to a later date, with questions such as who the end user is.
🗺️ Zoning change
County supervisors unanimously approved land-use plan changes for three big data center sites: La Osa near Eloy, Project Midway southwest of Casa Grande, and the W Holdings energy and tech campus south of Maricopa. These plan changes do not rezone the land; each site still needs a rezoning vote.
Drag the slider to compare the land before and now.
Where this comes from
- Pinal considering 215-acre data center development · AZBEX · July 2025
- Pinal County data center projects update · Rose Law Group Reporter · April 2026
- Pinal data center cases · AZBEX · 2026
- Pinal County Planning & Zoning Commission meeting, July 16, 2026 · Govly (meeting summary) · July 16, 2026
- Data center OK'd · InMaricopa · Nov 20, 2025
- OpenStreetMap: Midway Road meets Selma Highway · OpenStreetMap Nominatim · Oct 7, 2026