Send us a tip
ProposedBig (AI-size): 1,000 megawatts

Page data center campus near Horseshoe Bend

Also called: Page Data Center, Huntley LLC

A UK-linked company wants to buy 500 acres of city land near Horseshoe Bend for a 1-gigawatt data center campus. The City Council agreed to the sale, but the land still needs rezoning, and the developer must bring its own water and power. Many residents and a nearby Navajo chapter oppose it.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Page City.

Where things stand: Proposed City Council approved a land sale deal 5-2 in Oct 2025. That started a feasibility period; rezoning and other approvals are still needed.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Feb 2026): The LeChee Chapter of the Navajo Nation voted to oppose the land sale.

What we know

  • 📍 WhereAbout 500 acres of city land just southwest of the junction of U.S. 89 and State Route 98, less than a mile from Horseshoe Bend. Map point is southwest of that junction., Page, Coconino County
  • 🏢 CompanyHuntley LLC (linked to UK firm Rooskey)
  • 🌳 Size500 acres
  • ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)
  • 🔌 Where the power comes fromDeveloper must find its own power; may build power on site.
  • 💧 WaterDeveloper must find its own water; the city has not committed water.
  • ❄️ Coolingclosed-loop cooling required by the sale deal
  • 💵 Cost$10 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has the developer applied to rezone the land? 🙋 I'll find out ·
  • Where would the water and power come from? 🙋 I'll find out ·
  • Which company would use the data center? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Oct 22, 2025
      Page City Council passed Ordinance 744-25, 5-2, allowing a land sale of about 500 acres at $14,000 per acre.
    • Nov 2025
      Residents started a referendum drive; the city clerk later rejected it over paperwork errors.
    • Feb 2026
      The LeChee Chapter of the Navajo Nation voted to oppose the land sale.

    Local votes and rules

    🗺️ Zoning change

    Page City Council held a public hearing on Oct. 28 on proposed data center rules but did not vote. The planning commission will hold a hearing on Nov. 17, 2026. Ideas include mailing notices to residents within half a mile, two neighborhood meetings, proof of water and power, and a 55-decibel sound cap.

    Oct 28, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Horseshoe Bend uproar: Page locals rage over 1GW data hub deal · Hoodline · May 2026
    2. Did Page, AZ City Council approve the sale of 500 acres for a data center? Yes · Arizona Center for Investigative Reporting · Nov 21, 2025
    3. Page residents want voters to decide on planned data center · KNAU · Nov 18, 2025
    4. Page residents push back on $10B data center proposal near Horseshoe Bend · AZFamily · Dec 18, 2025
    5. Navajo Nation passes resolution · Salt Lake Tribune · May 10, 2026
    6. Proposed data center project in Page, one mile from Horseshoe Bend · ABC15 Arizona · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.