Proposed
Page data center campus near Horseshoe Bend
Also called: Page Data Center, Huntley LLC
A UK-linked company wants to buy 500 acres of city land near Horseshoe Bend for a 1-gigawatt data center campus. The City Council agreed to the sale, but the land still needs rezoning, and the developer must bring its own water and power. Many residents and a nearby Navajo chapter oppose it.
Where things stand: City Council approved a land sale deal 5-2 in Oct 2025. That started a feasibility period; rezoning and other approvals are still needed.
🕒 Latest update (Feb 2026): The LeChee Chapter of the Navajo Nation voted to oppose the land sale.
What we know
- 📍 WhereAbout 500 acres of city recreation land on Page's southwest edge, about a mile from Horseshoe Bend., Page, Coconino County
- 🏢 CompanyHuntley LLC (linked to UK firm Rooskey)
- 🌳 Size500 acres
- ⚡ Power it needs1,000 megawatts (about as much as 800,000 homes)
- 🔌 Where the power comes fromDeveloper must find its own power; may build power on site.
- 💧 WaterDeveloper must find its own water; the city has not committed water.
- ❄️ Coolingclosed-loop cooling required by the sale deal
- 💵 Cost$10 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has the developer applied to rezone the land? 🙋 I'll find out
- Where would the water and power come from? 🙋 I'll find out
- Which company would use the data center? 🙋 I'll find out
What happened so far
- Oct 22, 2025Page City Council passed Ordinance 744-25, 5-2, allowing a land sale of about 500 acres at $14,000 per acre.
- Nov 2025Residents started a referendum drive; the city clerk later rejected it over paperwork errors.
- Feb 2026The LeChee Chapter of the Navajo Nation voted to oppose the land sale.
🛰️ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Horseshoe Bend uproar: Page locals rage over 1GW data hub deal · Hoodline · May 2026
- Did Page, AZ City Council approve the sale of 500 acres for a data center? Yes · Arizona Center for Investigative Reporting · Nov 21, 2025
- Page residents want voters to decide on planned data center · KNAU · Nov 18, 2025
- Page residents push back on $10B data center proposal near Horseshoe Bend · AZFamily · Dec 18, 2025
- Navajo Nation passes resolution · Salt Lake Tribune · May 10, 2026