Send us a tip
ProposedBig (AI-size): 6,000 megawatts

AI data center campus near Apache Generating Station (Cochise)

Also called: SU26-22 191 Data Center and BESS, Apache Station AI campus

A company called Tombstone Resources wants to build up to nine large AI data center buildings (about 4.4 million square feet in all) and a battery storage system on about 747 acres of empty rangeland next to the Apache power plant near Cochise. At full size it would use up to 6 gigawatts of power, built in four phases. The application says it would be dry-cooled and use about 7 to 10 acre-feet of water a year, mostly for workers. SpaceX hosted the first community meeting; who will run the campus is not confirmed in county records.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ Last day to send a public comment: Friday, November 27, 2026, 12:00 PM Arizona Time (local time)

Last time to send written comments that will go in the packet for the Dec. 9 Planning and Zoning hearing. Later comments still go in the public record.

How: Send written comments to Cochise County Planning about case SU26-22; the county's Data Centers page explains how.

✔ ConfirmedSourceNot live: please check with the office first.

🗓️ Public hearing: Wednesday, December 9, 2026, 2:00 PM Arizona Time (local time)

Planning and Zoning Commission public hearing on the special use request (case SU26-22). The commission decides by majority vote; its decision can be appealed to the Board of Supervisors.

How: Attend at 1415 W. Melody Lane, Building G, Bisbee. Fill in a speaker request form ahead of time; each speaker gets about 2 minutes.

✔ ConfirmedSourceNot live: please check with the office first.

Where things stand: Proposed Application (case SU26-22) is under county review. Planning and Zoning Commission hearing set for Dec. 9, 2026. Nothing approved yet.

❓ 4 open questions about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Nov 4, 2026): A community town hall on the plan was held at Cochise Elementary School. The applicant's notice says SpaceX hosted it.

What we know

  • 📍 Whereeast of U.S. Highway 191 at Cochise, next to the Apache Generating Station (31 county parcels on two properties), Unincorporated Cochise County, Cochise County
  • 🏢 CompanyTombstone Resources L.L.C.
  • 🌳 Size747 acres
  • ⚡ Power it needs6,000 megawatts (about as much as 4,800,000 homes)
  • 🔌 Where the power comes fromPower from the grid through Sulphur Springs Valley Electric Cooperative and the Arizona Electric Power Cooperative (AEPCO), with a new substation on site, a large battery system, and natural-gas backup generators (about 10 MW per building) for critical needs (application)
  • 🗼 New power linesYes
  • 💧 WaterNo new well. Treated process water from the Apache Generating Station or trucked water; small on-site drinking water system (application)
  • ❄️ Coolingdry cooling, no cooling towers (application)
  • 👷 Jobs promised1,000

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who will own and run the data center? Is it SpaceX? 🙋 I'll find out ·
  • Who will pay if the power upgrades are built and the campus uses less power than planned? 🙋 I'll find out ·
  • How much air pollution would the natural-gas backup generators make, and will they need an air permit? 🙋 I'll find out ·
  • Did the county sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Nov 12, 2026: We checked the county's Data Centers page after the Nov. 12 emergency planning committee (LEPC) special meeting: no result is posted. The LEPC only advises; it does not approve or deny projects.

    What happened so far

    • Oct 2026
      Tombstone Resources applied to Cochise County for a special use permit (case SU26-22) for a data center campus and battery storage on about 747 acres.
    • Oct 13, 2026
      The developer met with county staff before applying (pre-application meeting), according to the application.
    • Nov 4, 2026
      A community town hall on the plan was held at Cochise Elementary School. The applicant's notice says SpaceX hosted it.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.