AIDEA industrial and energy district near Houston (possible data centers)

Also called: Houston Industrial Park, ADL 234762, Mat-Su Multi-Use Industrial and Energy Development District

The state wants to hand nearly 20,000 acres of public land near Houston to its economic development agency, AIDEA, for an industrial park. Data centers are one possible use, along with a rail hub and power lines. AIDEA says nothing is decided and no tenants are named. Houston leaders say they were left out.

โœ” ConfirmedSourceLast checked: Oct 8, 2026

Where things stand: The state proposed giving about 19,950 acres to AIDEA. Public comments were due in late summer 2026; no final decision found. No data center company has been picked.

๐Ÿ•’ Latest update (Aug 19, 2026): Original public comment deadline in the state notice (news reports say it was later extended).

What we know

  • ๐Ÿ“ WhereState land about 2 miles north of Houston (Townships 18N and 19N, Seward Meridian), bordering Willow, Meadow Lakes and Houston near the Parks Highway and Alaska Railroad; a small part is inside Houston city limits, Matanuska-Susitna Borough, Matanuska-Susitna Borough
  • ๐Ÿข CompanyAlaska Industrial Development and Export Authority (AIDEA)
  • ๐ŸŒณ Size19,950 acres
  • ๐Ÿ”Œ Where the power comes fromAIDEA lists power and gas line corridors as possible uses; no power plan yet.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • July 10, 2026
    The Department of Natural Resources proposed a no-cost transfer of about 19,950 acres of state land to AIDEA. AIDEA's plan lists 'scalable data centers' among possible uses.
  • Aug 13, 2026
    Houston City Council passed two resolutions objecting to how the state handled the transfer. A proposal to ban data centers in the city failed 4-2.
  • Aug 19, 2026
    Original public comment deadline in the state notice (news reports say it was later extended).

Local votes and rules

๐Ÿšซ Ban

A proposed city law to block data centers inside Houston city limits failed 4-2. Members who voted no said they want to ban data centers through general zoning rules instead. One member said he will propose a long-term pause while those rules are written.

Aug 13, 2026

๐Ÿ“Œ Other

The council voted unanimously against the state's process for moving about 30 square miles of state land near Houston to AIDEA, the state development agency. The land could hold an industrial park with data centers. The council said the city was left out of the decision.

Aug 13, 2026

๐Ÿค Agreement with the company

The Assembly voted 6-1 to override the mayor's veto and start a two-year partnership with Terra Energy Center Corp. Borough staff will help Terra find companies to build a data center or other big power user on borough land near Port MacKenzie, Big Lake or the planned West Susitna road. It does not require the borough to sell or lease land. The Assembly first passed it 5-2 on March 2.

March 17, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. New state proposal could bring data centers to the Mat-Su as part of industrial park ยท Alaska's News Source (KTUU) ยท July 16, 2026
  2. State proposes giving nearly 20,000 acres near Houston to AIDEA ยท Northern Alaska Environmental Center ยท July 22, 2026
  3. 'Zero transparency': Houston officials oppose land transfer process linked to data centers ยท Mat-Su Sentinel ยท Aug 18, 2026
  4. Proposed Land Conveyance to Alaska Industrial Development Export Authority near the city of Houston (ADL 234762) ยท Alaska Department of Natural Resources, Division of Mining, Land and Water ยท July 10, 2026

See something wrong? Tell us and we'll fix it.