USA › Ohio › Pickaway County

Pickaway County

1 data center project we know about. 24 townships, villages and cities.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

Local votes and rules

🗳️ Public vote · Ashville

Voters will decide whether to overturn the village council's April 2026 approval of a deal with developer EdgeConneX for two data center buildings and an 800-megawatt gas power plant. The Ohio Supreme Court ruled in August 2026 that the village could not use an 'emergency' label to block the vote. The county elections board still had to approve the petition.

Nov 3, 2026Source

⚖️ Court case · Ashville

The Ohio Supreme Court ruled that Ashville did not give real reasons for calling its data center approval an 'emergency.' That means residents can try to put it to a public vote (referendum).

Aug 2026Source

⏸️ Pause on new data centers · Washington

Township trustees passed a pause (moratorium) on new data centers that runs until July 2027.

June 2026Source

⚖️ Court case · Commercial Point

Residents sued to undo the village's May 2024 rezoning for data centers. They say council did not have enough votes to pass it as an emergency. In July 2026 a judge removed nine late-added plaintiffs and set a hearing on whether the rest can sue.

May 20, 2026Source

⚖️ Court case · Commercial Point

Amazon's development company K-Nova asked the Ohio Supreme Court to order the village to vote on its 'Project Cosmos' data center plan. It says the village cannot apply its new 18-month pause (moratorium) to a plan filed before the pause.

May 19, 2026Source

⏸️ Pause on new data centers · Commercial Point

Village council passed an 18-month pause (moratorium) on data center applications on May 4, 2026, as an emergency. Amazon's development company (K-Nova) is challenging it at the Ohio Supreme Court. It is set to end in November 2027.

May 4, 2026Source

⏸️ Pause on new data centers · South Bloomfield

Village council passed a six-month pause (moratorium) on new data centers. It is set to end in November 2026.

May 2026Source

✅ Approved · Ashville

Village council approved a deal (term summary) with developer EdgeConneX for two data center buildings and an 800-megawatt gas power plant. It was passed as an 'emergency' so it took effect right away.

April 2026Source

⏸️ Pause on new data centers · Scioto

Township trustees passed a one-year pause (moratorium) on new data centers. It is set to end in March 2027.

March 2026Source

⏸️ Pause on new data centers · Muhlenberg

Township trustees passed a one-year pause (moratorium) on new data centers. It is set to end in February 2027.

Feb 2026Source

⏸️ Pause on new data centers · Ashville

Village council passed a six-month pause (moratorium) on new data centers in December 2025, then extended it. It is set to end in January 2027. A separate data center deal with EdgeConneX was approved in April 2026 and is headed to a referendum.

Dec 2025Source