No project in Unincorporated Lyon County, but 2 nearby
Who decides here: the Lyon County Commission decides on zoning for land outside city and town limits.
Nearby (within 15 miles)
Tract Silver Springs data center park
Lyon County
1,060 acres
🕒 Sept 17, 2025: Tract bought about 1,060 acres after Lyon County approved rezoning and a development agr…
Reported in the news, not confirmed yet
Approved, not built yetabout 1 miles awayMonarch Data Center campus (Mason Valley)
Lyon County
505 acres
🕒 Aug 6, 2026: County commissioners approved the tentative rezoning 3-1 (one abstained).
Local votes and rules
🗺️ Zoning change · Lyon County
Lyon County commissioners voted 3-1 (one commissioner stepped aside) to approve the planned unit development rezoning for the Monarch Data Center and its gas power plant near Yerington. Copia Power has one year to file the final plan and still needs state permits. The Walker River Paiute and Yerington Paiute tribes said they would fight the decision in court.
📜 Data center rules · Lyon County
Lyon County commissioners reviewed a first draft data center ordinance at a workshop and voted 5-0 to send it back to staff. Several said the 150-foot buffer from homes was far too small. The draft would ban water-using cooling (except treated wastewater), require a permit in industrial zones, and set noise limits. It would not apply to Monarch.
✅ Approved · Lyon County
Lyon County's Planning Commission voted 4-3 to send the 1-gigawatt Monarch Data Center rezoning on to the County Commission.
🗺️ Zoning change · Lyon County
Lyon County commissioners voted 4-1 to change the master plan for the Monarch Data Center site in Mason Valley from farmland (Agriculture) to Specific Plan. This did not approve building anything; a rezoning was still needed.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Lyon County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Sierra Pacific Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Nevada.