Cumberland County
3 data center projects we know about. 10 towns, cities and unincorporated areas.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Projects
PRSM Group AI data center
Cumberland County, Cumberland County
50 acres
🕒 Nov 12, 2026: The county attorney told commissioners the data center rules will not be ready before th…
Reported in the news, not confirmed yet
ProposedDunn Road data center (Energy Storage Solutions)
Fayetteville, Cumberland County
50 acres
🕒 Oct 26, 2026: City Council voted 6-4 for new zoning rules: a warehouse meant to hold a data center nee…
ProposedCuster Avenue data center (Terra Nexus Ventures)
Fayetteville, Cumberland County
180 acres
🕒 Oct 26, 2026: City Council voted 6-4 for new zoning rules: a warehouse meant to hold a data center nee…
Reported in the news, not confirmed yet
Local votes and rules
⏸️ Pause on new data centers · Cumberland County
The county's six-month data center pause ends Dec. 15, and the new data center rules will not be ready by then. The county plans to extend the pause by up to six months, ending early once the rules pass. A public hearing and vote are planned for Dec. 14.
📜 Data center rules · Fayetteville
City Council voted 6-4 to change the city's zoning rules for data centers. A warehouse that would hold a data center now needs a conditional rezoning, which means a council review. Reports say the rules also cover noise, utilities, lighting, air quality and a 24-hour contact person. The change only takes effect once the city holds its public hearing on a proposed data center pause. That hearing date has not been set.
📜 Data center rules · Unincorporated Cumberland County
The county planning board approved draft data center rules on Oct. 20. County commissioners are set to take them up on Nov. 12, with a final vote expected in December. Data centers would only be allowed on manufacturing land with commissioner approval. Buildings would have to be 800 feet from property lines (1,200 feet in some cases near homes) and 2,000 feet from schools, churches, hospitals and day cares. Water cooling would have to reuse water (closed loop). The county's pause on data centers runs to about Dec. 15, 2026. The rules would also cover the Town of Eastover.
⏸️ Pause on new data centers · Fayetteville
At a special meeting, City Council voted 6-4 to hold a public hearing on a proposed data center pause and told staff to write the pause first. It also told staff to update the proposed data center rules (noise, setbacks, buffers). No hearing date has been announced.
⏸️ Pause on new data centers · Cumberland County
Cumberland County paused data center building in unincorporated areas for six months. Staff will write data center rules in the meantime. Concerns included power, water and noise.
📌 Other · Fayetteville
Fayetteville City Council voted 6-3 not to pass a data center pause yet, and to study the issue for 120 more days instead. On April 13 it had voted 5-4 to stop work on a data center ordinance and look at a pause.
Find your town
In North Carolina, cities and towns decide inside their limits. Outside them, the county decides.