📣 Report Something
USA › Maine › Washington County

Washington County

1 data center project we know about. 48 towns, uts, plantations, cities and reservations.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

Local votes and rules

🚫 Ban · Eastport

Eastport City Council unanimously adopted a resident-backed ordinance banning large data centers, including underwater ones like the DeepGreen plan. It turned down a second petition that would have made big projects need a town vote; city lawyers called it unlawful. The council plans to make the ban stronger and clearer.

Sept 9, 2026Source

⏸️ Pause on new data centers · Eastport

Eastport City Council unanimously passed a 180-day pause on industrial data centers, on land or underwater. The city cannot approve permits for them during the pause. It came after the DeepGreen underwater data center plan.

Aug 12, 2026Source